“it is a triumph more glorious, because far more useful to mankind, than was ever won by conqueror on the field of battle. May the Atlantic telegraph, under the blessing of heaven, prove to be a bond of perpetual peace and friendship between the kindred nations, and an instrument destined by Divine Providence to diffuse religion, civilization, liberty, and law throughout the world.

(US President James Buchanans telegrammed reply to Queen Victoria over the first transatlantic cable.)

BallinskelligPCa

Each letter of the first messages across the Atlantic ocean took over two minutes to send due to bad reception. Compare this to the 84 billion words per second (at the time of writing) over fibre-optic cable, this seems pitifully slow, enough to drive most of us to distraction in our high speed high tech world. But in the 1870’s it was a huge step forward in international communications and one of the first sparks in the information superhighway we take for granted today.
The Skelligs coastline from Valentia Island to Ballinskelligs and Waterville played a huge part in this link as the landing site of the first Transatlantic Cables and the site of the first cable stations.
Here is the history of the Cable Station in Ballinskelligs and the laying of the cables.

Ballinskelligs Cable Station

ballinskelligWhile the first commercial cable station was established in Valentia in 1866, competition soon arrived in the form of a British company (Direct United States Cable Company). In 1874 the company established a cable station in Ballinskelligs. Soon after however the Anglo American Cable Company took a majority shareholding in the British company and a connecting cable was laid from the Ballinskelligs station to the Valentia cable station.
Anglo American subsequently leased the line to the telecommunications company Western Union who continued the lease up until 1920. The business was then sold to the British Post Office. The British Post office diverted the European end of the cable to Cornwall in 1923 and the Ballinskelligs cable station was closed.
The Cable station buildings became government property soon after their closure and in the 1930’s and 40’s were used as a summer college for Irish language students. They later fell into disrepair and most have now been demolished.

The History of the Transatlantic Cable

imagesWhile the converted steamer ‘Great Eastern’ had been used to lay the first transatlantic cable in 1872, in the following year an English company built the first special cable-laying ship, the ‘Hooper’. This encouraged William Siemens to build a cable steamship himself, based on this vessel and his own extensive experience, which he christened ‘Faraday’ in honour of his friend Michael Faraday.
Its main distinguishing features were the two paddlewheels on the sides which had previously only been seen on American riverboats, and the additional rudder on the bow which made the Faraday extremely manoeuvrable. Superstructures on the deck also made it possible to lay the cable via the bow or the stern. After its completion in spring 1874, the steamer set out at eight o’clock on May 16 on its first transatlantic crossing.
The first cable-laying
Before the main submarine stretch was tackled, the cable between Newfoundland and the United States was laid. The first section went from Halifax in Nova Scotia to Portsmouth in New Hampshire. The next section went from Nova Scotia to Newfoundland, though they were prohibited from going on land in Newfoundland due to the monopoly of the Anglo American Telegraph Company. According to the letters that the brothers wrote to one another, the work was completed at the beginning of August. The Faraday returned to the UK, and Carl wrote to Werner and William about the “shore end,” in Torbay in Newfoundland. The spot where the cable was brought ashore, however, is marked today by the Tor Bay Atlantic Provincial Park in Nova Scotia.
Route of the transatlantic cable
20110915_bild_3_karte_steckenfuehrung_transatlantikkabel_458pxThe laying of the actual Atlantic cable probably began between the middle and end of August. According to Pole, the biographer of William Siemens, the Faraday set out to sea again on August 26 and began laying the cable near the Irish coastal village of Ballinskelligs. From this point on Werner von Siemens was there in person. The laying had hardly begun when disaster struck, as reported by Werner himself:
“[…] but when I arrived early this morning on my Irish cart in the usual ghastly rain from my hotel 16 English miles away, I was met by long faces. There was a defect in the cable, which the ship was trying to recover.”
The cable had broken, and so deep down that the entire Mont Blanc could have been sunk in the sea at this point. It took seven hours for the grapnel which was lowered to search for the cable to reach the sea bed. A cable had never been recovered from such a depth before. But Carl achieved the impossible: within two days the lost cable was picked up and the laying could continue. Werner wrote to Berlin with relief:
‘The recovery of the cable from such a great depth (2,580 fathoms) and its repair all within a day is something new in this field and will establish our reputation!’
It was to take another year….
However, the project was not further blessed with good fortune. The Faraday had to fish up and repair the cable several times, until a shortage of coal and stormy weather forced the ‘unhappy cable squadron’ to return to Ireland. There could however be no question of abandoning the cable, since this would have meant a huge loss of prestige for the Direct United States Cable Company and the Siemens brothers.
At the end of October the Faraday was already on its way again – and once more had bad luck. Near Newfoundland the cable was lost again in a storm, and this time the ship was damaged as well. Because of the necessary repair work and the permanently bad weather it was no longer possible to think of completing the cable before the end of 1874. It was not until the beginning of April that the Faraday set sail again, and in June 1875 a link was established between Torbay and Ballinskelligs Bay for the first time.
However, the cable was still not operating properly. There were repeated interruptions, which had a very negative effect on both the costs and the mood of those involved. William reported several times to Werner that the Direct United shareholders were demanding that Carl be replaced as director of the project on board the ship.
e004414150In the middle of August the search for the fault was recommenced and this time the crew succeeded in finding the defect in the cable. At the beginning of September a permanent link between the stations in Torbay and Ballinskelligs Bay was achieved. Werner was relieved:
“So at last the cable is working perfectly! Thank God this nightmare is over.”
Shortly afterwards it was handed over to the public, and on September 15, 1875 Carl wrote as follows: “Today is the opening day! I hope to hear soon how the dispatching is going.” It evidently went very well: the cable beat that of the competition hands down. Carl reported from London:
‘The cable is continuing to operate well. On the first day the stock exchange people held a competition and the DUS beat the English [the competition] by more than an hour.’
They had made it!